Demonstration Site Preconditions
The following outline indicates known
preconditions that must be met prior to undertaking the redesign and
implementation of the Demonstration Sites.
Demonstration Site
1
Hart House Green - Queen's Park - Wellesley
Street
1. City approval of the removal of the
Queen's Park Crescent overpass and the pedestrian improvements to
the district is required prior to site development.
2. Portions of the western side of this
site could proceed prior to approval outlined above.
Demonstration Site 2 King's College Circle
- Convocation Hall Plaza - King's College Road - St. George Linkages
1. Replacement of surface parking could
be a precondition for site development.
Demonstration Site 3
Back Campus
1. Replacement of surface parking could
be a precondition for site development.
Demonstration Site 4
Willcocks Street - Sidney Smith Hall
- New College - Huron Street
1. Willcocks Street and Huron Street
modifications will require City of Toronto approval.
2. No preconditions apply to the New
College courtyard.
3. The development character of Sidney
Smith Hall should be known before the new West Campus open space on
Willcocks Street is created.
Demonstration Site 5
College Street
1. No preconditions apply to College
Street.
2. The Taddle Creek Road forecourt open
space should be associated with the construction activity of Development
Site 15.
Demonstration Site 6
Spadina Circle - Russell Street
1. Spadina Circle should be associated
with the construction activity related to Development Site 7.
2. The walkways at the head of Russell
Street should be associated with the construction of Development Site
10, with the exception of the walkway to the University Visitor Centre,
which could proceed immediately.
3. Changes to Russell Street would require
City of Toronto approval.
|